Excavation calculator
Enter the size and side slope to see how much soil you dig and how many loads it makes.
About Excavation Calculator
Digging a hole produces more loose soil than the hole itself, because soil swells when it is broken up. This tool gives you both numbers. Choose a trench or a pit, type the bottom length and width, the depth and the side slope. A slope of zero means vertical sides. The volume is worked out for sloped sides, then increased by a swell percentage and divided by the capacity of your truck to give the number of loads.
- Estimating spoil to remove from a foundation.
- Pricing a drain or pipe trench.
- Planning how many truck trips to book.
- Seeing how side slope increases the volume.
How to use Excavation Calculator
Step 1
Pick trench or pit and enter the bottom size and depth.
Step 2
Enter the side slope, the swell percentage and the truck capacity.
Step 3
Read the volume to dig and the loads.
Good to know
- Worked example: a 20 m trench, 1 m wide and 1.5 m deep with vertical sides is 30 m³ in the ground. At 25 percent swell that is 37.5 m³ loose, or 4 loads of 10 m³.
- Swell varies a lot. Sand swells less than clay, and rock swells more. Use a figure from your own site experience.
- Deep excavations need shoring or sloped sides for safety. Ask a qualified engineer, because this tool does not assess stability.
Common questions
What is swell?
It is the increase in volume when soil is dug out and loosened. A 25 percent swell means 1 m³ in the ground becomes 1.25 m³ in a truck.
What does a side slope of 0.5 mean?
The top edge sits 0.5 m out from the bottom edge for every 1 m of depth, on each side.
Is the truck capacity heaped or level?
Enter whatever your hauler quotes. This tool uses the number you type as the volume per load.